Water leaks out of the east side of Broad Ripple Dam. A $2 million repair is planned by city’s Department of Waterworks as part of rate case. (IBJ Photo/Robin Jerstad)
Water leaks out of the east side of Broad Ripple Dam. A $2 million repair is planned by city’s Department of Waterworks as part of rate case. (IBJ Photo/Robin Jerstad)

Chris O'Malley, The IBJ

comalley@ibj.com

Already swamped with higher debt costs due to a bond refinancing fiasco, the city's Department of Waterworks is priming next for a battle over capital projects that include repairs to a crucial dam.

Among projects that would be funded by a general rate case the department plans to file with regulators on Sept. 30 is construction of a water intake at its flagship treatment plant, at a cost of $27.5 million. Shoring up the dam spanning the White River, in Broad Ripple, will cost another $2 million.

The dam-parts of which predate Thomas Edison's invention of the light bulb-raises the shallow river high enough to spill into the Central Canal and on down to a water treatment plant northwest of downtown.

The dam and the canal it feeds are crucial to the lifeblood of the city, both literally and economically. They account for 60 percent of the city's water supply, or 90 million gallons a day.

The proposed $27.5 million intake, which would tap into the White River closer to the treatment plant, would serve as an emergency backup in the event the dam or canal fails. The alternative intake could also be used temporarily during canal maintenance.

Though the proposed dam project by comparison is a sliver of the capital request to be submitted, it is a crucial part of the water system's infrastructure.

High water last February lifted two large slabs of concrete from the apron on the downstream side of the nearly 10-foot-tall dam, according to department records.

"If the dam fails, then there will be insufficient raw water flow from the White River through the canal to the White River Treatment Plant," the department stated in a recent filing with the Indiana Utility Regulatory Commission.

The filing states the department intends to spend $683,000 on design and permitting for an interim dam on the White River and to develop a preliminary cost estimate for a permanent replacement of the existing dam.

Such a replacement-likely costing several million dollars-will not be included in the upcoming general rate case, said Jo Lynn Garing, spokeswoman for the Department of Waterworks.

Stability in question

A large section of concrete missing from a portion of the dam is of "particular concern," said engineers from ATC Associates Inc., who inspected the dam in July of last year.

"While there is no indication that this or any other observable condition presents an immediate threat to the integrity of the dam, it is recommended that the damaged portion of the apron be repaired in the relatively near future since a progressive deterioration in a relatively short period of time cannot be ruled out for a dam of this age," wrote engineers James Luckiewicz and David Warder.

They recommended the dam be inspected monthly. The Indiana Department of Natural Resources generally inspects so-called low-head dams of this type only about once every five years.

The dam has some seepage and there are some holes and notches in the concrete, but the ATC engineers said it "appears to be in generally good condition and functioning properly."

"We don't anticipate a catastrophic failure of the dam," Garing said.

But the city's primary water supply system is showing its age and vulnerability.

According to the ATC report, the concrete portion of the dam appeared to have been built sometime before 1921. Portions of the original dam-on its outer edges near the shore-date back to the 1830s, when the canal was dug between Broad Ripple and downtown. It was for a short time a channel for small boats and part of a broader offshoot of the Erie Canal system.

The original portion of the dam was built with an intricate system of logs overlain by a triangular structure that consisted of alternating layers of wooden planks and boulders, according to an inspection report. In some places, cribs made of wood planks were filled with boulders.

Another firm hired by the department, HNTB, said in a meeting last June with city and DNR officials that the dam was showing its age.

The approach recommended at that meeting was that the department begin design and construction of a temporary replacement dam upstream of the existing one.

"Develop emergency action plan to address failure of, or impending failure of, sections of the dam," stated a document from HNTB filed with the DNR. "Start construction of temporary replacement structure-as soon as regulatory permits received."

Garing reiterated that the department did not see any danger of imminent dam failure and that a replacement was probably at least three years out.

The consequences of a canal failure were underscored in 1992, when an earthen wall collapsed, stopping the flow of water to the White River treatment plant. In what earned headlines nationwide, the city imposed emergency water usage restrictions and boil-water orders as construction crews scrambled to rebuild the canal wall.

A long 'to do' list

Water department officials did not have a list of other projects or a grand total of capital projects ready to disclose before the Sept. 30 filing.

"We have a lot of 'got to do' projects," said Matthew Klein, the department's executive director since March. Previously, Klein was head of enforcement at the Indiana Department of Environmental Management.

On the list will be any number of replacements of portions of the water system's 4,000 miles of pipes, along with mandated upgrades in water quality equipment. The U.S. Environmental Protection Agency has given water utilities until 2012 to install ultraviolet disinfection systems as an additional safeguard against cryptosporidium and giardia, which cause gastrointestinal illness.

The department already has spent $12 million at White River and may need to spend an additional $16 million on two other plants.

Those are among the $163 million in capital projects through 2012 intended for the city's water system-part of more than $600 million in repairs and upgrades eyed for the next 15 years, according to a solicitation for ideas Mayor Greg Ballard released in July.

"That is what's driving this rate case-it's capital improvements," Garing said.

Another rate hike

The city's water system, Indianapolis Water Co., is operated for the waterworks department under a contract with French-owned Veolia Water. Earlier this year, the IURC approved an emergency rate hike of 12.3 percent-or $3 per month-for the average residential customer, to help the department blunt the effects of more than $25 million in additional annual debt-service costs. The department had sought a nearly 18-percent emergency rate hike.

The department's debt soared after financial markets collapsed late last year.

In 2005, in what looked like a no-brainer way to free up an extra $45 million in extra cash for capital projects, the department, through the Indianapolis Bond Bank, converted fixed-rate bonds to variable rate with such abandon that variable issues grew to about 60 percent of its $845 million in outstanding bond debt.

Bond swaps intended to mitigate the risk of interest-rate variations failed to backstop the risk as financial firms involved in the deal collapsed or saw their credit ratings plunge. The result was higher interest rates that in some case rose to 9.5 percent from 3.5 percent. The department is converting variable-rate debt back to fixed, but the cost is in the tens of millions of dollars, spread over decades.

The consequences of what was in hindsight a foolish refinancing strategy will now be borne by ratepayers. Industrial water users, in particular, are boiling mad.

"We will be looking at all aspects of their case very critically," said Bette J. Dodd, an attorney at Lewis & Kappes PC, which is representing industrial water customers before the IURC.

Klein noted the criticism the IURC leveled at the department during the emergency rate case. He said one goal of the general rate case is to boost confidence in the department's financial, managerial and technical capabilities.

Copyright © 2024 All Rights Reserved.